Bathrooms were the most common remodeling project in 2025. In the National Association of Home Builders' survey of remodelers for the fourth quarter of 2025, 73% rated bathroom remodels as common or very common, ahead of kitchens. The question we hear first from Richmond homeowners is how long they will be without the room. Here is a realistic picture of a bathroom remodel with Kitchen and Bath Experts, from first visit to final walkthrough. For kitchens, see our kitchen remodel timeline.
The short answer
For a typical hall bath or primary bath that keeps the same layout, construction itself usually takes a few weeks. Planning, selections, ordering and permits come before that, and they often take as long as the construction. A larger primary bath with moved plumbing, a curbless shower or custom glass takes longer.
Phase 1: Design and selections
- In-home consultation and measuring. We look at the room, the plumbing, the floor structure and what you want to change.
- Design and layout. Deciding on the shower size, the vanity and the tile layout. See our primary bathroom ideas and small bathroom ideas.
- Selections. Tile, vanity, countertop, fixtures, lighting and glass. Making every selection before work starts is the single best way to keep a project on schedule.
Phase 2: Ordering and permits
- Ordering. Vanities, specialty fixtures and some tile have lead times. We schedule construction around delivery dates so the bathroom is not torn apart while you wait for parts.
- Permits. Plumbing, electrical and structural work generally need permits in Richmond, Henrico and Chesterfield. See our permits guide.
Phase 3: Construction
- Protection and demolition. We protect floors and the path to the bathroom, then remove the old fixtures, tile and drywall.
- Discovery and repairs. Once walls and floors are open, we can see any water damage, rot or outdated plumbing. This is where hidden problems show up, especially in older Richmond homes. See remodeling an older home.
- Rough plumbing and electrical. New supply lines, drains, valves, wiring, lighting and the exhaust fan. Inspections happen here when required.
- Backer board and waterproofing. The shower walls and floor get a complete waterproofing system and are tested before tile. See shower waterproofing.
- Tile. Floors, shower walls and any accent walls. Tile is usually the longest single step, and grout needs time to cure.
- Vanity, countertop and fixtures. Vanity, top, faucets, toilet, shower trim and accessories.
- Glass, paint and trim. Frameless shower glass is usually measured after tile is finished, so it is one of the last items installed. See our shower glass guide.
- Final inspection and walkthrough. We go through every detail with you and fix anything on the punch list.
What causes delays
- Changing selections after work starts. It is the most common cause of delays and cost increases.
- Back-ordered materials. Specialty tile or fixtures can arrive late, which is why we order early.
- Hidden damage. Rotted subfloor or framing under an old shower must be repaired before anything else.
- Inspection scheduling. Busy seasons can add a few days between steps.
- Custom glass. Fabrication after measurement adds time at the end.
Living through it
If it is your only shower, plan ahead. Many families shower at the gym or with a neighbor, or we schedule the project around a trip. If you have a second bathroom, most households barely notice the work after the first few days of demolition. See how to prepare your home for a remodel.
Frequently asked questions
Can a bathroom be remodeled in a week? Swapping a vanity or toilet, yes. A full remodel with new tile and waterproofing needs more time because of inspections, curing and glass.
Why does tile take so long? Every cut around niches, valves and corners is done by hand, and mortar and grout need curing time.
Do I need to move out? Rarely. Most homeowners stay home. Dust control and a clean work site keep the rest of the house livable.
Know your schedule before we start
We give you a written schedule with your fixed price, so you know when each phase happens. Schedule a free in-home consultation.